ANALISIS KINERJA PROYEK TERHADAP KETEPATAN WAKTU, ANGGARAN DAN PENGADAAAN SUMBER DAYA PROYEK
DOI:
https://doi.org/10.51878/academia.v6i2.11417Keywords:
Kinerja Proyek, Anggaran, Keterlambatan, Pengadaan Sumber DayaAbstract
Low labor productivity, weather dynamics, site changes, and material logistics constraints often trigger delays and cost overruns on PT SMJ's large-scale construction projects. This phenomenon underscores the importance of a comprehensive evaluation of operational control efficiency. This study focuses on analyzing project performance in terms of timeliness, budget availability, and resource procurement effectiveness. The methodology was systematically implemented through a questionnaire survey of 150 expert respondents, followed by statistical modeling using SmartPLS-based Structural Equation Modeling (SEM). Quantitative test results indicate that this model has a high fit, with an SRMR value of 0.045 and an NFI of 0.945. Path coefficient evaluation demonstrates that the budget has a very strong positive and significant influence on project performance, with an original sample value of 0.796 and a T-statistic of 6.368. Furthermore, resource procurement is listed as the most dominant determinant influencing budget stability, with a path coefficient of 0.834. The main conclusion of the study confirms that successful construction project performance relies heavily on the accuracy of operational budget management. Strict supply chain oversight and the use of the critical path method are recommended to mitigate the risk of delays and optimize financial efficiency in the field.
ABSTRAK
Rendahnya produktivitas tenaga kerja, dinamika cuaca, perubahan lapangan, serta hambatan logistik material sering memicu keterlambatan dan pembengkakan biaya pada proyek konstruksi skala besar PT SMJ. Fenomena ini melatarbelakangi pentingnya evaluasi komprehensif terhadap efisiensi kendali operasional. Fokus penelitian ini adalah menganalisis kinerja proyek terhadap ketepatan waktu, ketersediaan anggaran, dan efektivitas pengadaan sumber daya. Metodologi dijalankan secara sistematis melalui survei kuesioner kepada 150 responden ahli, yang dilanjutkan dengan pemodelan statistik Structural Equation Modelling (SEM) berbasis SmartPLS. Data kuantitatif hasil pengujian menunjukkan bahwa model ini memiliki kesesuaian tinggi dengan nilai SRMR sebesar 0,045 dan NFI mencapai 0,945. Evaluasi koefisien jalur membuktikan bahwa anggaran memiliki pengaruh positif dan signifikan yang sangat kuat terhadap kinerja proyek dengan nilai original sampel sebesar 0,796 serta T-Statistik mencapai 6,368. Selain itu, pengadaan sumber daya tercatat sebagai faktor penentu paling dominan yang memengaruhi stabilitas anggaran dengan koefisien jalur sebesar 0,834. Simpulan utama penelitian menegaskan bahwa kesuksesan performa proyek konstruksi sangat bertumpu pada akurasi pengelolaan anggaran operasional. Pengawasan ketat pada rantai pasok dan pemanfaatan metode jalur kritis disarankan secara konkret untuk memitigasi risiko keterlambatan serta mengoptimalkan efisiensi pembiayaan di lapangan.
Downloads
References
Ariyasa Qadri, R., Hendra Pratama, R., Khabibi, A., Syam Pratama, R., & Author, C. (2024). Refining the cash-waqf blended finance model for infrastructure development. Management and Accounting Review, 23(1), 45–60.
Ayusar, F. I., Widyawati, R., & Despa, D. (2023). Kajian produksi kontrol sebagai pengendalian dengan sistem swakelola dan harga distribusi (Studi kasus: Pengadaan material aggregat di proyek preservasi Sp. Blusuh – Batas Kalteng, Kalimantan Timur). Seminar Nasional Insinyur Profesional (SNIP), 3(1). https://doi.org/10.23960/snip.v3i1.412
Balbuena, S. (2023). Application of the Rasch model in streamlining an instrument measuring depression among college students. International Journal of Assessment Tools in Education, 10(2), 257–278. https://doi.org/10.21449/ijate.1210479
Bilgin, G., Erol, H., Atasoy, G., Dikmen, ?., & Birgönül, M. T. (2022). Exploring pattern of complexity in mega construction projects. International Journal of Managing Projects in Business, 15(7), 1064–1090. https://doi.org/10.1108/ijmpb-03-2022-0064
Chomistriana, D., Mulyono, A. T., Najid, N., & Bagio, T. H. (2024). The impact of construction stakeholder’s readiness and acceptance of technology on the success of Indonesian digital government transformation in construction sector. Uncertain Supply Chain Management, 12(2), 841–856. https://doi.org/10.5267/j.uscm.2024.1.003
Daryono, R. W., Hidayat, N., Nurtanto, M., & Fuadi, A. (2024). The development of a competency framework for architectural engineering graduates: Perspectives by the construction industry in Indonesia. Journal of Technology and Science Education, 14(2), 274–285. https://doi.org/10.3926/jotse.1986
Denicol, J., Davies, A., & Krystallis, I. (2020). What are the causes and cures of poor megaproject performance? A systematic literature review and research agenda. Project Management Journal, 51(3), 328–345. https://doi.org/10.1177/8756972819896113
Djaelani, M., Putra, A. R., Darmawan, D., Lestari, U. P., & Retnowati, E. (2022). Perencanaan biaya menggunakan perhitungan biaya riil pada proyek perumahan. PADURAKSA: Jurnal Teknik Sipil Universitas Warmadewa, 11(2), 207–213. https://doi.org/10.22225/pd.11.2.5363.207-213
Emaminejad, N., Kath, L. M., & Akhavian, R. (2024). Assessing trust in construction AI-powered collaborative robots using structural equation modeling. Journal of Computing in Civil Engineering, 38(3), Article 04024005. https://doi.org/10.1061/jccee5.cpeng-5660
Farid, P., Klakegg, O. J., & Bakke, C. (2025). Mega construction projects: Governance challenges for the project owner. Procedia Computer Science, 256, 1474–1481. https://doi.org/10.1016/j.procs.2025.02.281
Fatimatuzzahro, S., & Adiwati, M. R. (2026). Analisis penerapan purchasing dalam mendukung kinerja operasional (Studi kasus PT Indo Bismar). CENDEKIA: Jurnal Ilmu Pengetahuan, 6(1), 422–430. https://doi.org/10.51878/cendekia.v6i1.8885
Fikri, K. (2026). Peran pengelola teknis dalam perencanaan pembangunan dan pengawasan bangunan gedung Puskesmas Cugung Lalang Kabupaten Kepahiang [Tesis, Universitas Andalas]. Andalas University eThesis.
Hutajulu, J. M. J., Djunaidi, A., & Triwahyuni, A. (2021). Properti psikometri Beck Hopelessness Scale pada populasi non-klinis Indonesia. Intuisi: Jurnal Psikologi Ilmiah, 13(1), 24–37. https://doi.org/10.15294/intuisi.v13i1.28037
Imro’atun, N., & Chairudin, M. (2026). Pengaruh penggunaan Gemini sebagai alat bantu penulisan terhadap kualitas karya ilmiah mahasiswa. LEARNING: Jurnal Inovasi Penelitian Pendidikan Dan Pembelajaran, 6(2), 1152–1163. https://doi.org/10.51878/learning.v6i2.9634
Indriyani, D., Azzahra, N. F., Sabila, A. F. N., Juniarti, R. A., & Suhendi, S. (2026). Analisis anggaran sederhana pada UMKM: Studi kasus Kedai Masakanna Panyileukan. CENDEKIA: Jurnal Ilmu Pengetahuan, 6(3), 1553–1563. https://doi.org/10.51878/cendekia.v6i3.10833
Khadafi, M., Nuri, S., Maulina, I., Rikeniateni, R., & Munasarah, M. (2024). Dampak anggaran biaya operasional terhadap profitabilitas perusahaan. MENAWAN: Jurnal Riset Dan Publikasi Ilmu Ekonomi, 3(1), 1–9. https://doi.org/10.61132/menawan.v3i1.1030
Kubanov, R., Makatora, D., & Yashchenko, O. (2024). Motivational mechanism of an architectural and construction manager’s activity. Business Inform, 8(559), 399–412. https://doi.org/10.32933/2222-4459-2024-8-399-412
Nainggolan, E. O., & Maghfiroh, R. D. (2026). Pemanfaatan data operasional harian dalam pengambilan keputusan berbasis data di PT Delta Jaya Mas. CENDEKIA: Jurnal Ilmu Pengetahuan, 6(1), 149–159. https://doi.org/10.51878/cendekia.v6i1.8882
Nanda, Y. D., & Adiwati, M. R. (2026). Peran administrasi purchasing dalam efisiensi pengelolaan keuangan perusahaan (Studi kasus pada PT Indo Bismar Surabaya). CENDEKIA: Jurnal Ilmu Pengetahuan, 6(1), 442–452. https://doi.org/10.51878/cendekia.v6i1.8887
Rahman, R. D., & Maghfiroh, R. D. (2026). Quality control sebagai sistem preventif analisis akar penyebab defect produk pada PT Delta Jaya Mas. CENDEKIA: Jurnal Ilmu Pengetahuan, 6(1), 382–391. https://doi.org/10.51878/cendekia.v6i1.8881
Rahmania, A., Triwahyuni, A., & Kadiyono, A. L. (2022). Validitas konstruk Growth Mindset Scale: Versi Bahasa Indonesia. Jurnal Psikologi, 18(2), 194–204. https://doi.org/10.24014/jp.v18i2.16925
Risjad, M. N., & Anondho, B. (2020). Validasi prediksi durasi dengan metode earned schedule untuk gedung bertingkat di Jakarta. JMTS: Jurnal Mitra Teknik Sipil, 3(2), 237–246. https://doi.org/10.24912/jmts.v3i2.7072
Rochima, A., & Citalada, M. B. D. A. (2026). Optimalisasi pengelolaan database data proyek konstruksi di bagian admin data pada PT. CENDEKIA: Jurnal Ilmu Pengetahuan, 6(2), 774–784. https://doi.org/10.51878/cendekia.v6i2.9337
Rosmiati, R., Putra, I., & Nasori, A. (2021). Pengukuran mutu pembelajaran di FKIP UNJA dalam upaya membangun generasi economic citizen yang mengelaborasi program MBKBM Kemendikbud. EDUKATIF: JURNAL ILMU PENDIDIKAN, 3(6), 5256–5264. https://doi.org/10.31004/edukatif.v3i6.1356
Sari, P. M. (2023). Kualitas laporan keuangan UMKM berbasis SAK EMKM: Self efficacy sebagai variabel moderasi. OIKOS: Jurnal Kajian Pendidikan Ekonomi Dan Ilmu Ekonomi, 7(1), 164–176. https://doi.org/10.23969/oikos.v7i1.5917
Sarifudin, M., & Asmara, R. Y. (2023). Pengaruh kompetensi auditor, sistem pengendalian mutu, kode etik terhadap kualitas audit dan dampaknya pada stakeholders. Buletin Studi Ekonomi, 28(1), 1–12. https://doi.org/10.24843/bse.2023.v28.i01.p01
Vogelsmeier, L. V. D. E., Jongerling, J., & Maassen, E. (2024). Assessing and accounting for measurement in intensive longitudinal studies: Current practices, considerations, and avenues for improvement. Quality of Life Research, 33(8), 2107–2118. https://doi.org/10.1007/s11136-024-03678-0
Winarno, S., Nuryanto, H., & Teguh, M. (2022). Efficiency of the use of materials of concrete block against rubble stone on shallow foundation works. MEDIA KOMUNIKASI TEKNIK SIPIL, 28(1), 67–78. https://doi.org/10.14710/mkts.v28i1.37541
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 Josua Riski Silaen, Muhammad Sobirin, Syafiatun Siregar

This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.













